LOAD-OUT OLD NAVY CRANE



Project Summary

In June of 2005, a 500 t heavy old Navy crane was skidding onto the Hickey Marine crane barge CRYSTAL GAYLE at the Hunters Point Shipyard in San Francisco. The 4 story high legs and boogies of the crane were first removed and the whole crane was lowered down to ground level. Using skid shoes and hydraulic push-pull units, the crane was slowly pushed onto the barge, over skid track and bridge beams. During the skidding operation, the barge was continuously ballasted to compensate for the weight coming onboard, as well as for the changes in tide.

Scope of Work

The project scope included:


   


Project Photographs














specialists in marine heavy-lift transportation engineering
naval architects
marine surveyors


If you can read this and do not see a MENU here, please allow for scripts to run
Est. 1992


Copyright © 2012 Argonautics Marine Engineering, Inc. - All Rights Reserved
Home  Services  |  Projects  |  News  |  Clients  |  Publications  |  References  |  About Us  |  Contact Us  |  Client Login  |

Model the crane barge hull and all its void spaces;
Simulation of the crane skid-on and optimization of ballast procedures; 
Provide on-site assistance during the actual load-out operation.
Hunter Point crane loaded onto barge
Hunter Point Navy crane successfully loaded onto barge
Push unit behind skid shoe
Push unit behind skid shoe
Skid shoe on bridge beam
Skid shoe on bridge beam
Front skidshoes on barge
Front skidshoes on barge
Deballasting barge after loading
Deballasting barge after loading