MATING MOLIKPAQ


Project Summary

In March through May of 1998, Argonautics Marine Engineering, Inc. was part of a multi-national team of specialists, involved in the
mating operation of the MOLIKPAQ rig onto a purpose built spacer structure in Okpo, Korea.

The MOLIKPAQ, a bottom founded, mobile arctic caisson type rig, has been refurbished by Daewoo Heavy Industries, Ltd. in Okpo,
Korea for installation offshore Sakhalin. Since this new location is in deeper waters, a 16 m high steel structure was designed and
built to increase the rig's hull depth. This "spacer" was built in sections at the Amur Shipbuilding Plant and assembled in Bolshoi
Kamen. The octagonal, donut shaped 15,000 t heavy spacer measured 110 x 110 m and was outfitted with 3 stability towers. A
hydraulic operated valve system was installed for gravity ballasting. The Ballast Control Container was mounted on the center
buoyancy tower. Upon completion in Russia, the spacer was towed to the Daewoo Heavy Industries, Ltd. shipyard for final
preparations and testing before the mating operation. Computer simulations were used to optimize the spacer submersion procedure.

On May 23, the spacer was towed out to the carefully selected mating site and moored to a spread of pre-installed anchors and
winch barges. A work barge, outfitted with generators and compressors (providing the compressed air needed for deballasting) was
hooked up to the center tower. Following the procedure, the spacer was slowly submerged by free flooding the large main ballast
tanks while maintaining trim and heel control with the smaller corner tanks.

On May 26, the MOLIKPAQ was towed to the mating site and connected to the anchored winch barges. While monitoring the
position relative to the submersed spacer with underwater cameras, the MOLIKPAQ was slowly winched into position against 3
stoppers. Once in position, the spacer was deballasted, lifting the 43,000 t MOLIKPAQ out of the water. Final position of the
MOLIKPAQ was confirmed to be within 5 mm, well within the 50 mm tolerance. The successfully mated units were unmoored and
towed back to the yard for welding of the MOLIKPAQ bottom to the spacer pedestal tops and completion of the refurbishing.  In
August of 1998, the rig was towed to Sakhalin and successfully set down at its new offshore location.

Scope of Work

The project scope included:











A short video shows the mating operation and welding of the drilling unit to the spacer structure, all filmed by Daewoo. Requires
Windows Media Player.

A project paper presented at the Northern California Section meeting of the SNAME, Berkeley, CA, on June 10, 1999, can be
downloaded in PDF format.

  

Project Photographs















specialists in marine heavy-lift transportation engineering
naval architects
marine surveyors


If you can read this and do not see a MENU here, please allow for scripts to run
Est. 1992


Copyright © 2000 Argonautics Marine Engineering, Inc. - All Rights Reserved
Home  Services  |  Projects  |  News  |  Clients  |  Publications  |  References  |  About Us  |  Contact Us  |  Client Login  |

Attending and working as a member of the Mating Task Force Team;
Reviewing of all engineering output and procedures;
Reducing the planned offshore time from 14 days to 5 days;
Providing experience and operational input for the procedures;
Design of safe and workable ballast procedures for the spacer submersion;
On-site training of the Daewoo ballast team;
Supervision of the actual spacer ballast and MOLIKPAQ mating operations.
Lifting 4-th street bridge with barge
Mated MOLIKPAQ during final deballasting of the spacer
Spacer arrived at the Daewoo yard
Spacer arrived at the Daewoo yard
Spacer deck starting to submerse
Spacer deck starting to submerse
Maneuvering the rig in position over the spacer
Maneuvering the rig in position over the spacer
Deballasting the spacer
Deballasting the spacer